S.NoName of the CustomerNature of WorkWork Order Value (In lakhs)Work Completed %Year of Starting
1 M/s. TATA PROJECTS LIMITED
Ground improvement work using Non-vibratory stone column Method and Band Drains (PVD) Techniques
11006.83 Just Started 2018
2 M/s. A.G.GROUP Piling work for Construction of Storied Building for Project "Z" at 47 Canal Circular Road, Kolkata 710.00 10% Work Completed 2018
3 M/s. AMBUJA NEOTIA - KOLKATA Installation of Bored Cast-In-Situ piles of 1.0M dia for Luxury Tower A&E at Mukundapur, Kolkata WO-II 690.00 50% Work Completed 2018
4 M/s. NCC Ltd - AMARAVATHI Piling work for MLA Quarters in Amaravathi, Vijayawada 1785.00 80% Work Completed 2017
5 M/s. NCC Ltd - CHENNAI Installation of Bored Cast in-situ piles for Chennai Metro Rail Work in Wimco Nagar Section - Chennai 787.00 80% Work Completed 2017
6 M/s. ITDC LTD Hiring of Casagrande B400 Hydraulic Piling Rig with D'Wall Kit 350.00 95% Work Completed 2017
TOTAL WORK IN PROGRESS VALUE